title: "UPS for data centres: how to choose and plan | AEC"
url: https://www.aecups.com/en/blog/ups-for-data-centres/
description: "A data centre UPS should be online double conversion, sized on measured IT load plus growth. Worked example, rack and modular options, N+1/2N, batteries."
language: en
---

15 July 2022 · updated 3 November 2026 · 9 min

# UPS for data centres: how to choose and plan

A data centre UPS keeps servers, storage and network equipment running without a break when the mains fails or dips, until the generator starts or the systems shut down. Most sites need an online double-conversion UPS sized on the measured IT load plus growth, from a 2U IST3-J to a modular IST6 of up to 1,200 kVA.

Reviewed by **[Bruno Grosso](https://www.aecups.com/en/about/#bruno-grosso)** and **[Eng. CP Cheng](https://www.aecups.com/en/about/#cp-cheng)**, with an associate project engineer, AEC Engineering

Plan it with N+1 or 2N redundancy and batteries in a cool, controlled space.

**In brief**

- Choose an **online double-conversion** UPS (class VFI under [IEC 62040-3](https://webstore.iec.ch/en/publication/60140)): in normal operation the load is isolated from mains disturbances.
- Size on the **measured IT load in kW**, add the growth you expect and keep a working margin of about 20%.
- **Small data centres and server rooms** often fit a rack UPS of 1–40 kVA; larger sites usually choose a modular UPS that grows module by module.
- Plan **redundancy** (N+1 or 2N), the **battery room** and **efficiency** together, because each one drives the others.

## What a data centre UPS has to do

Even a short interruption can corrupt databases, break transactions and start hours of recovery work. The UPS (uninterruptible power supply) is the part of the power chain that prevents it.

It has three jobs. First, it carries the load through mains failures, from a dip of a few milliseconds to a full blackout. Second, it cleans the supply: spikes, sags, harmonics and frequency drift stay on the input side. Third, it gives the generator time to start and take over, or gives the IT systems time to shut down safely.

Only an online double-conversion UPS does all three without any transfer time. The rectifier turns the mains into DC, the inverter rebuilds a clean sine wave, and the battery sits on the DC bus ready to take over. [IEC 62040-3](https://webstore.iec.ch/en/publication/60140) calls this class VFI (voltage and frequency independent). Our guide to [online, line-interactive and offline UPS](https://www.aecups.com/en/blog/ups-types-online-line-interactive-offline/) explains why the other types are not suited to IT loads of this kind.

## How to size a data centre UPS

Sizing starts from the load. Measure the real power drawn by the IT equipment in kW, ideally from the rack power distribution units (PDUs) over a few weeks. Server nameplates usually overstate the real draw.

Then add the growth you expect over the life of the UPS and a working margin. Running a UPS at 100% leaves no room for load steps or a new rack, so a target of about 75–80% at the planned load is common practice. Finally, check the output power factor: many modern UPS have a unity power factor, so kVA equals kW. Our guide to [kVA vs kW](https://www.aecups.com/en/blog/kva-vs-kw/) explains the conversion when it is not 1.

### Worked example: a small data centre

A company runs 12 racks. The PDUs show an average of 4 kW per rack.

1. Load today: 12 × 4 kW = **48 kW**.
2. Expected growth: six more racks over five years, so 18 × 4 kW = **72 kW**.
3. Working margin: 72 kW ÷ 0.8 = **90 kW** of UPS capacity needed in year five.
4. Power factor: with an output power factor of 1, 90 kW = 90 kVA.
5. Modular solution: the [IST6 30–120 kVA](https://www.aecups.com/en/products/ist6-120/) uses 30 kVA / 30 kW modules. Today, 48 kW ÷ 0.8 = 60 kW, so 2 modules plus 1 spare for N+1 = **3 modules**. In year five, 3 modules plus 1 spare = **4 modules**, in the same cabinet.
6. Backup time: for 10 minutes at 72 kW, the load needs 72 kW × 10/60 h = 12 kWh at the UPS output. The battery must supply more, to cover the inverter losses (about 12 ÷ 0.95 ≈ 12.6 kWh at 95% efficiency), plus an allowance for battery ageing.

One cabinet grows from 90 to 120 kVA installed, with one module of redundancy throughout. The [UPS backup time guide](https://www.aecups.com/en/blog/ups-backup-time/) and the [backup time calculator](https://www.aecups.com/en/tools/backup-time/) take the battery step further.

## Which UPS for server rooms, small and large data centres

The right form of UPS depends mostly on the size of the load: the principles stay the same, the hardware does not.

**AEC UPS ranges by type of site (figures from the AEC range pages)**

| Site | Typical approach | AEC range | Key figures |
| --- | --- | --- | --- |
| Server room, single rack | Rack UPS in the same 19-inch cabinet | [IST3-J](https://www.aecups.com/en/products/ist3-j/) | Single-phase online, 1–10 kVA, 2U; battery box 2U in the same rack |
| Server room or edge site, three-phase | Three-phase rack UPS | [IST9](https://www.aecups.com/en/products/ist9/) | 10–40 kVA in a 3U chassis, up to 96% efficiency, output PF 1 |
| IT room with no space for a battery cabinet | UPS and battery in one cabinet | [All-in-One](https://www.aecups.com/en/products/all-in-one/) | 20 kVA, hot-swappable lithium modules, up to 200 min at 6 kW with 8 × 50 Ah modules |
| Small to medium data centre | Modular UPS, 30 kVA steps | [IST6 30–120 kVA](https://www.aecups.com/en/products/ist6-120/) | 30 kVA modules, fifth slot for N+1, 97% in double conversion |
| Medium to large data centre | Modular UPS, 50 kVA steps | [IST6 200–500 kVA](https://www.aecups.com/en/products/ist6-200-500/) | Up to 98.1% efficiency, THDi ≤ 1.5%, up to 8 UPS in parallel |
| Large data centre | Modular UPS, 100 kVA steps | [IST6 400–1200 kVA](https://www.aecups.com/en/products/ist6-400-1200/) | Up to 98.1% with PLUS modules, 1.2 MW in 1.2 m², 9.6 MW with 8 UPS |

### Rack UPS for server rooms and small data centres

A server room UPS often lives in the rack it protects. The IST3-J is 2U high on every model from 1 to 10 kVA, and its battery box mounts in the same rack below it. Optional programmable outlets can switch off non-critical loads after a set time on battery, to save backup time for the servers that matter.

When the room needs three-phase power, the IST9 puts a 10–40 kVA online UPS into 3U of a 19-inch cabinet. It runs in 3/3 or 3/1 configuration (1/1 up to 20 kVA), and the same unit also stands as a tower.

### Modular UPS for growing data centres

Once the load passes a few tens of kW and keeps growing, a modular UPS usually makes more sense: capacity grows one module at a time and a spare module gives N+1 in the same cabinet. Our [modular UPS guide](https://www.aecups.com/en/blog/modular-ups/) covers how the IST6 family works in detail.

## Redundancy: N, N+1 and 2N

Redundancy is the spare capacity that keeps the load supplied when part of the UPS system fails or is under maintenance. "N" is the capacity the load needs. Take a data centre with a 500 kW load:

| Level | Configuration | What it protects against |
| --- | --- | --- |
| N | One UPS system sized for 500 kW | Mains failures; not a UPS fault |
| N+1 | Units or modules in parallel, with one more than the load needs | Mains failures and the failure of one unit or module |
| 2N | Two independent systems, each able to carry 500 kW, one per power path | Mains failures, a UPS failure and faults on one distribution path |

For 2N to work, the IT equipment needs dual power supplies connected to both paths. The IST6 200–500 kVA supports up to eight UPS in parallel in dual-bus and multi-bus layouts. On the IST6 ranges, N+X redundancy works at two levels: spare modules inside each cabinet, and spare UPS within the parallel system.

Our guide to [UPS redundancy, N+1 and 2N](https://www.aecups.com/en/blog/ups-redundancy-n-plus-1/) goes through the options, their weak points and how to test them.

## Batteries and where to put them

Larger data centres usually keep the UPS and batteries in a dedicated room, separate from the IT space. The batteries are the main reason. A widely used rule of thumb says VRLA battery life roughly halves for every 8 °C above 25 °C, so lead-acid batteries need a cool, controlled room. AEC gives 20–30 °C as the best battery temperature for the IST6 30–120 kVA.

The UPS itself is more tolerant: the IST6 400–1200 kVA runs without derating up to 40 °C, provided the cooling airflow is planned.

Lithium iron phosphate (LFP) batteries take less floor space than lead-acid. The [L6 lithium system](https://www.aecups.com/en/products/l6-lithium/) stores up to 69 kWh per cabinet with 100 Ah modules, grows to fifteen cabinets in parallel and serves AEC UPS from 6 to 1200 kVA. For lead-acid, AEC supplies [battery cabinets](https://www.aecups.com/en/products/battery-cabinets/) with 12 V AGM batteries. Our comparison of [VRLA and lithium UPS batteries](https://www.aecups.com/en/blog/ups-batteries-vrla-vs-lithium/) sets out the trade-offs.

## Efficiency, heat and power quality

A data centre UPS runs day and night, so its losses run day and night too. Every kW lost in the UPS becomes heat that the cooling system must then remove. The losses follow a simple formula: losses = P × (1/η − 1), where P is the load and η the efficiency.

Take a 240 kW load. At 97% efficiency, losses are 240 × (1/0.97 − 1) ≈ 7.4 kW. At 95%, they are 240 × (1/0.95 − 1) ≈ 12.6 kW. That is about 5.2 kW of extra heat, or roughly 45,600 kWh a year over 8,760 hours, before counting the cooling. Always compare efficiency at your real load, not only at full load.

Power quality on the input side matters as much. A low input current distortion (THDi) and an input power factor close to 1 reduce the stress on cables, transformers and the generator. The IST6 200–500 kVA has an input THDi of 1.5% or less at full load and an input power factor of 0.99 or more. Our guide to the [UPS and generator](https://www.aecups.com/en/blog/ups-and-generator/) explains why this helps when the generator is supplying the site.

## Generator, monitoring and service

The UPS battery covers minutes; the generator covers hours. The two must be planned together. On the IST6 ranges, dry contacts can start the generator when the mains fails. On the IST6 30–120 kVA, battery charging can also be disabled while the generator runs.

Connect the UPS to the building management system and the network. The IST6 ranges offer Modbus, RS232 and RS485 as standard, and an optional [SNMP card](https://www.aecups.com/en/products/snmp-card/) adds network monitoring, alerts and remote shutdown. On the IST6 30–120 and 200–500 kVA the touch screen keeps 10,000 event records, which helps to trace a fault.

Agree a maintenance plan that includes regular battery tests, and make sure engineers and spare modules are available quickly. AEC offers 24/7 technical assistance by phone and WhatsApp.

## Checklist before you choose

- Measured IT load in kW, per rack and in total.
- Expected growth over five to ten years, and when it will arrive.
- Required redundancy level: N, N+1 or 2N, and whether the IT equipment has dual power supplies.
- Backup time needed until the generator takes over or until a controlled shutdown.
- Battery technology and the space, floor loading and temperature of the battery room.
- Supply: three-phase 400 V or single-phase, and the generator rating.
- Monitoring: BMS, SNMP and shutdown software for the servers.
- Service: response times, spare modules and battery replacement plan.

## Common mistakes

- **Sizing from nameplates.** Server nameplates overstate the real draw, and the UPS ends up oversized and running at low efficiency.
- **Forgetting growth.** A UPS sized only for today's load may need replacing within a few years.
- **Counting on 2N with single-corded loads.** Equipment with one power supply sees only one path, so it loses the benefit of 2N.
- **Batteries in a warm room.** VRLA batteries kept well above 25 °C age much faster than planned.
- **No generator test with the UPS.** The pair should be tested together under load, not only one at a time.

If you send us the load, the growth plan and the backup time you need, we can propose a configuration. Use the [UPS finder](https://www.aecups.com/en/tools/ups-finder/) for a first shortlist, or [contact AEC](https://www.aecups.com/en/contacts/#form) for a data centre project. Sites in the Middle East have a page of their own: [UPS for data centres in the Middle East](https://www.aecups.com/en/applications/middle-east-data-centres/).

Questions

## Questions people ask

#### What type of UPS is used in a data centre?

Data centres use online double-conversion UPS, class VFI under IEC 62040-3. The inverter supplies the load all the time, so in normal operation mains disturbances do not reach the servers and there is no transfer time when the mains fails. Larger sites usually choose modular systems for growth and redundancy.

#### How do I size a UPS for a small data centre or server room?

Measure the real IT load in kW, add the growth you expect over the life of the UPS, and divide by about 0.8 to keep a working margin. For example, 72 kW of planned load needs about 90 kW of UPS capacity. Add one module or unit for N+1 if the site needs redundancy.

#### What is the difference between N+1 and 2N?

N+1 adds one spare unit or module to the same system. 2N uses two completely independent systems, each able to carry the whole load, on separate power paths. 2N only protects fully when the IT equipment has dual power supplies.

#### Can a rack UPS protect a server room?

Yes, for smaller loads. The IST3-J is a 2U single-phase online UPS from 1 to 10 kVA, and the IST9 puts a 10–40 kVA three-phase online UPS into a 3U rack chassis. Above a few tens of kW, or when the load will grow, a modular UPS is usually the better fit.

#### Should the UPS batteries be in the server room?

Yes, if the temperature is controlled, but larger sites use a separate room. A widely used rule of thumb says VRLA battery life roughly halves for every 8 °C above 25 °C. Lithium batteries such as the L6 system take less floor space.

#### Is a modular UPS better for a data centre?

Yes, for data centres whose load will grow and that need redundancy and service without shutdown. For a stable, smaller load, a conventional online UPS can be enough, and several units can still run in parallel.

Products

## Products in this guide

[All products](https://www.aecups.com/en/products/)

### IST6-120

VRLA

30–120 kVA

Modular online UPS, double conversion, 30–120 kVA

Details

### IST6 200–500

VRLA

200–500 kVA

Modular online UPS, double conversion, 200–500 kVA

Details

### IST6 400–1200

VRLA

400–1200 kVA

Modular online UPS, double conversion, 400–1200 kVA

Details

### L6 Lithium

Lithium

40 · 50 · 100 Ah

Modular lithium battery system, 40 · 50 · 100 Ah

Details

Blog

## Keep reading

[All articles](https://www.aecups.com/en/blog/)

[**UPS redundancy: N+1 or 2N, and how much a site needs** UPS redundancy explained: what N, N+1, N+X and 2N mean, parallel vs modular UPS, a worked 90 kW example, a comparison table and a checklist.](https://www.aecups.com/en/blog/ups-redundancy-n-plus-1/) [**Online UPS vs line-interactive vs offline: UPS types** The three UPS types compared: offline, line-interactive and online double conversion, with transfer time, VFI/VI/VFD classes and ECO mode.](https://www.aecups.com/en/blog/ups-types-online-line-interactive-offline/) [**UPS vs CPSS: which one does a building need?** A UPS keeps equipment running; a CPSS keeps safety systems such as emergency lighting on. How they differ and when a building needs both.](https://www.aecups.com/en/blog/ups-vs-cpss/)

## Talk to an AEC engineer

Tell us the load, the supply and the backup time you need: we answer with the model and the batteries that fit.

[Contact us](https://www.aecups.com/en/contacts/#form) [+39 02 9415 8991](tel:+390294158991)