title: "IST6-120 UPS questions and answers | AEC"
url: https://www.aecups.com/en/faq/ist6-120/
description: "17 questions about the AEC IST6-120: choosing the model, backup time, installation, communication and service, each with its answer and its page."
language: en
---

Questions and answers

# IST6-120: questions and answers

17 questions about the AEC IST6-120, from its range page and its 4 model pages, grouped by subject. Each answer is the one printed on its page; follow the link for the full data, the tables and the drawings.

[IST6-120](https://www.aecups.com/en/products/ist6-120/) [All questions](https://www.aecups.com/en/faq/)

## Choosing, sizing and ordering 8 questions

#### How does the IST6-120 grow with the load?

The cabinet takes 30 kVA / 30 kW power modules (2U, 24 kg): 30, 60, 90 or 120 kVA with 1 to 4 modules, added online in free slots with no new footprint. Beyond 120 kVA, several IST6 cabinets work in parallel with the parallel kit.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

#### How many modules do I need for N+1 redundancy?

Install one module more than the load needs: 2 modules for 30 kVA, 3 for 60 kVA, 4 for 90 kVA, and 4 plus a module in the dedicated fifth redundancy slot for 120 kVA. If a module stops, the others carry the load without transfer to bypass.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

#### Can a power module be replaced without shutting down the UPS?

Yes: power modules are inserted and removed online, a faulty module is isolated automatically, and the 3U bypass module is removable. Wait at least 10 minutes after removal before opening a module; replacement is done by AEC or authorised personnel.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

#### Can a 120 kVA IST6 be redundant in one cabinet?

Yes: four modules carry 120 kVA and a fifth module goes in the dedicated redundancy slot (N+1). Two system control cards and a centralised, removable bypass module complete the redundancy.

Answered on [IST6-120, 4 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-120k-4x30/)

#### Is one module enough for a 30 kVA load?

Yes: one IST6-30-J carries 30 kVA / 30 kW. For redundancy the catalogue's table gives two modules (N+1) for loads up to 30 kVA: a module can then stop or be replaced while the other keeps the load on the inverter.

Answered on [IST6-120, 1 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-30k-1x30/)

#### How many modules for 60 kVA with redundancy?

Three: two carry the load (N = 2) and the third is the redundant one (N+1), as in the catalogue's table. Each module is 30 kVA / 30 kW, 2U and 24 kg.

Answered on [IST6-120, 2 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-60k-2x30/)

#### Can a module be replaced with the load on?

Yes. Each module has a ready switch and RUN / ALARM / FAULT LEDs; a faulty module is isolated automatically and replaced online. Wait at least 10 minutes after removal before opening it; replacement by AEC or authorised personnel.

Answered on [IST6-120, 2 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-60k-2x30/)

#### What is the best way to get 90 kVA N+1?

Four IST6-30-J modules in one IST6-120 cabinet: three carry the load, one is redundant. The catalogue's scalability table lists exactly this: 90 kVA, 3 modules, 4 for N+1.

Answered on [IST6-120, 3 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-90k-3x30/)

## Backup time and batteries 3 questions

#### Which batteries does the IST6-120 use?

A split battery of ±14 to ±23 × 12 V blocks (±168 to ±276 V DC), default ±16; with fewer than ±16 blocks the load is limited to 80%. Charging current is up to 10 A per power module, lead-acid or lithium with the optional BMS card, and parallel cabinets can share one battery group.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

#### How long does a 120 kVA UPS like the IST6-120, 4 × 30 kVA run?

3 to 221 minutes at full load (120 kW), and 9 to 442 minutes at half load, with the AEC battery options in the table: the battery chosen sets the figure. With 34 × 12 V 80 Ah (IST6-120-34X80): 3 minutes at 100% and 9 at 50%. For other loads and batteries use the backup-time tool.

Answered on [IST6-120, 4 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-120k-4x30/)

#### What charging current does the IST6-120 give with three modules?

Up to 30 A: the charging current is 10 A per power module (maximum), 40 A with four. Lead-acid or lithium with the BMS expansion card.

Answered on [IST6-120, 3 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-90k-3x30/)

## Installation, size and connections 3 questions

#### What space does the IST6-120 need?

The cabinet measures 600 × 860 × 2000 mm and weighs 195 kg without power modules. Leave at least 800 mm at the front and rear and 500 mm above; cables enter from the bottom as standard, or from the top with the top wiring accessory.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

#### What cables does a full IST6-120 need?

From the user manual: mains input 213 A, 1 × (4 × 120) mm²; bypass input and output 182 A, 1 × (4 × 95) mm²; battery at ±16 blocks 330 A nominal, 377 A maximum, 1 × (3 × 95) mm². Size on site to local rules and cable length.

Answered on [IST6-120, 4 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-120k-4x30/)

#### IST6-120: how big is each model and how much does it weigh?

Width × depth × height and weight, model by model:

| Model | Size | Weight |
| --- | --- | --- |
| [IST6-120, 1 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-30k-1x30/) | 600 × 860 × 2000 mm | 195 kg + 1 × 24 kg module |
| [IST6-120, 2 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-60k-2x30/) | 600 × 860 × 2000 mm | 195 kg + 2 × 24 kg modules |
| [IST6-120, 3 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-90k-3x30/) | 600 × 860 × 2000 mm | 195 kg + 3 × 24 kg modules |
| [IST6-120, 4 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-120k-4x30/) | 600 × 860 × 2000 mm | 195 kg + 4 × 24 kg modules |

Size and weight from the EMEA 2026 catalogue.

Each model's own page, linked in the table, gives its full answer and data.

## Communication and monitoring 1 question

#### Which communication options does the IST6-120 offer?

Modbus on RJ45, RS232, RS485, two EPO inputs and 4 dry-contact inputs / 3 outputs are standard (7 + 5 with the expansion card). An SNMP card with a temperature and humidity sensor port and a BMS expansion card are optional.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

## Efficiency and operation 1 question

#### How efficient is the IST6-120?

97% in online double conversion and up to 99% in ECO mode, plus a redundancy sleep function for spare modules at light load. At 96 kW, AEC's indicative calculation gives 2.97 kW of losses in double conversion against 0.97 kW in ECO mode.

Answered on [IST6-120](https://www.aecups.com/en/products/ist6-120/)

## Warranty, service and maintenance 1 question

#### How is power added later?

By sliding further 30 kVA modules into the free slots, numbered 1 to 5 from the bottom, with the load running. Modules are added and configured by AEC service; beyond 120 kVA, more cabinets join with the parallel kit PAR-IST6.

Answered on [IST6-120, 1 × 30 kVA](https://www.aecups.com/en/products/ist6-120/ist6-30k-1x30/)

## By range

## Still a question?

Tell us the load, the supply and the backup time you need: AEC answers with the model and the batteries.

[Contact AEC](https://www.aecups.com/en/contacts/#form) [Blog](https://www.aecups.com/en/blog/)