# 208 V vs 480 V: choosing a three-phase UPS

In the US a three-phase UPS is either 208 V (208Y/120 V, most commercial buildings) or 480 V (480Y/277 V, large buildings and plants). Below about 100 kVA the UPS usually goes on the 208 V panel that feeds the room; above it, 480 V carries the same power at less than half the current. The building decides which, and the size of the load decides whether to change it.

Reviewed by **[Bruno Grosso](https://www.aecups.com/us/about/#bruno-grosso)** and **[Eng. CP Cheng](https://www.aecups.com/us/about/#cp-cheng)**, with an associate project engineer, AEC Engineering · Updated November 17, 2026

7 min read

## What are the two US three-phase supplies?

- **208Y/120 V** The supply of most US commercial buildings: 208 V between phases, 120 V from phase to neutral for the receptacles. Server rooms, offices, retail, clinics.
- **480Y/277 V** The service of large commercial and industrial buildings: 480 V between phases, 277 V to neutral for lighting. Transformers step it down to 208Y/120 V for the receptacles.
- **The rule of thumb** A UPS goes on the voltage of the panel it feeds. Large loads are usually cheaper to carry at 480 V, then stepped down close to the racks.

## How much current per kVA?

Three-phase current is the power divided by (√3 × voltage):

| UPS rating | At 208 V | At 480 V |
| --- | --- | --- |
| 30 kVA | 83 A | 36 A |
| 100 kVA | 278 A | 120 A |
| 300 kVA | 833 A | 361 A |

Less current means smaller cables and breakers, which is why loads past roughly a hundred kVA usually move to 480 V.

## What does it mean for the feeder?

A UPS feeder carries a continuous load, so the National Electrical Code, [NFPA 70](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70), sizes its conductors and breaker at 125 % of the current. Take 150 kVA:

- **At 208 V**: 416 A per phase, 520 A at 125 %. That is usually two parallel sets of conductors in two raceways, and a large frame breaker.
- **At 480 V**: 180 A per phase, 226 A at 125 %: one set of conductors.

Voltage drop follows the same way. For the same power on the same cable, the drop in percent scales with 1 ÷ V², so at 480 V it is about a fifth of what it would be at 208 V ((208 ÷ 480)² = 0.19). On a long run from the switchgear to the UPS room, that alone can decide the voltage. The final sizes belong to the engineer of record, from the NEC tables and the installation manual.

## Where does the transformer go?

Most 480 V buildings still feed their receptacles at 208Y/120 V, through a step-down transformer. The UPS can sit on either side of it:

- **UPS at 208 V, transformer upstream.** The UPS goes on the 208 V panel of the room. Simple, and the usual answer for a server room in an existing building.
- **UPS at 480 V, transformer downstream.** The UPS sits near the switchgear and feeds power distribution units with their own transformers, close to the racks. The usual answer for data centers: the long runs carry 480 V, and the transformer creates the new neutral the 120 V loads need.

## Which 30 kVA UPS: 208 V or 480 V?

At 30 kVA both supplies are common, and AEC offers a UPS for each. From the 2026 catalog, new batteries:

| Model | Supply | Build | Current at 30 kVA | Runtime at full / 75 % load |
| --- | --- | --- | --- | --- |
| [ETH30-3X50A-LI](https://www.aecups.com/us/products/etherno/eth30-3x50a-li/) | 208 V, 4-wire | Tower, three 50 Ah lithium modules | 83.3 A | 14 / 17.5 min |
| [AUR30-80X9A](https://www.aecups.com/us/products/aureon/aur30-80x9a/) | 208 V, 4-wire | Tower, 80 VRLA blocks | 83.3 A | 4 / 7 min |
| [RAD90-2X15](https://www.aecups.com/us/products/radiant/rad90-2x15/) | 208 V, 4-wire | Modular, two 15 kVA modules, external bank | 83.3 A | Sized with the bank |
| [CIRIB150-1X30](https://www.aecups.com/us/products/cirro-ib/cirib150-1x30/) | 480/277 V, 4-wire | Modular, one 30 kVA module, VRLA trays inside | 36.1 A | 14 / 25 min |

A 30 kVA modular UPS at 480 V carries less than half the current of a 208 V one, and the CIRRO-IB frame has four free slots for growth to 150 kVA. At 208 V, the RADIANT frame grows to 90 kVA in 15 kVA steps.

## 3-wire or 4-wire?

A 4-wire supply carries a neutral; a 3-wire one does not. [CIRRO](https://www.aecups.com/us/products/cirro/) and [CIRRO-IB](https://www.aecups.com/us/products/cirro-ib/) are 480/277 V, 4-wire. [INFINITE](https://www.aecups.com/us/products/infinite/) is 480 V, 3-wire: loads that need a neutral are fed through a transformer downstream. [RADIANT](https://www.aecups.com/us/products/radiant/) takes 208/120 V three-phase in and gives three-phase or single-phase out.

## Which AEC UPS fits each supply?

| Supply | Power | AEC series |
| --- | --- | --- |
| **Single-phase 120 V** | 1–3 kVA | [LUMINA](https://www.aecups.com/us/products/lumina/), [FERRUS](https://www.aecups.com/us/products/ferrus/), [FERRUS RT](https://www.aecups.com/us/products/ferrus-rt/) |
| **Split-phase 120/240 V** | 6–20 kVA | [FERRUS SP](https://www.aecups.com/us/products/ferrus-sp/), [FERRUS SP RT](https://www.aecups.com/us/products/ferrus-sp-rt/) |
| **Three-phase 208 V** | 10–100 kVA | [ETHERNO](https://www.aecups.com/us/products/etherno/), [AUREON](https://www.aecups.com/us/products/aureon/), [RADIANT](https://www.aecups.com/us/products/radiant/), [RADIANT-IB](https://www.aecups.com/us/products/radiant-ib/) |
| **Three-phase 480 V** | 30–1,600 kVA | [CIRRO-IB](https://www.aecups.com/us/products/cirro-ib/), [CIRRO](https://www.aecups.com/us/products/cirro/), [INFINITE](https://www.aecups.com/us/products/infinite/), [INFINITE 1.5MW](https://www.aecups.com/us/products/infinite-1-5mw/) |

## Which one should you choose?

- **Up to about 100 kVA in an ordinary building:** 208 V, on the panel that feeds the room: [ETHERNO](https://www.aecups.com/us/products/etherno/) or [AUREON](https://www.aecups.com/us/products/aureon/) (10 to 30 kVA), [RADIANT](https://www.aecups.com/us/products/radiant/) (15 to 90 kVA), [RADIANT-IB](https://www.aecups.com/us/products/radiant-ib/) (20 to 100 kVA).
- **Large loads, data centers, plants:** 480 V: CIRRO-IB (30 to 150 kVA), CIRRO (60 to 1,600 kVA), INFINITE (100 to 600 kVA) and INFINITE 1.5MW (750 to 1,500 kVA).
- **Between the two:** ask us with the single-line diagram; the answer depends on where the switchgear and the loads sit.

The [UPS sizing tool](https://www.aecups.com/us/tools/ups-sizing/) takes the supply voltage, the load in kW, kVA or amps and the minutes, and lists the AEC models that fit.

## What mistakes come up with US voltages?

- **Reading 208 V as 220 V or 240 V.** 208 V is the line-to-line voltage of a 120 V wye; 240 V is a split-phase or delta service. ETHERNO is rated 208 V (220/208 V); a 240 V split-phase panel takes a FERRUS SP instead.
- **Using the wrong voltage in the formula.** Three-phase current uses the line-to-line voltage: 208 or 480, never 120 or 277.
- **Forgetting the neutral.** A 3-wire 480 V UPS has no neutral at its output. Loads at 277 V or 120 V need a 4-wire UPS such as CIRRO, or a transformer.
- **Ignoring the generator.** If the generator and its transfer switch are 480 V and the room is 208 V, the step-down transformer sits between them, and its inrush and losses go into the plan.

## Questions people ask

#### What is the difference between a 208 V and a 480 V UPS?

They match the two US three-phase supplies: 208Y/120 V in most commercial buildings, 480Y/277 V in large commercial and industrial ones. At 480 V the same power draws less than half the current.

#### Can a 480 V UPS feed 208 V loads?

Yes, through a step-down transformer between the UPS and the loads, which is how most US data centers are built.

#### How many amps does a 100 kVA UPS draw?

About 278 A at 208 V and about 120 A at 480 V (kVA × 1,000 ÷ (√3 × volts)), before the input current of the charger and losses.

#### Which AEC UPS works on 208 V?

ETHERNO (lithium) and AUREON (VRLA) from 10 to 30 kVA, RADIANT modular from 15 to 90 kVA and RADIANT-IB from 20 to 100 kVA.

#### Is there a 30 kVA modular UPS for 480 V?

Yes: the AEC CIRRO-IB CIRIB150-1X30, one 30 kVA module in a 150 kVA frame at 480/277 V, with its VRLA batteries inside: 14 minutes at full load and 25 at 75 % from the catalog table.

## Sources

1. [NFPA 70, National Electrical Code (NFPA)](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70)

More guides: [How long do UPS batteries last? VRLA and lithium](https://www.aecups.com/us/blog/ups-battery-life/) [Data center UPS: modular, 480 V and lithium](https://www.aecups.com/us/blog/data-center-ups/) [How to size a UPS: five steps to the power you need](https://www.aecups.com/us/blog/ups-sizing/) [How to read a UPS datasheet, line by line](https://www.aecups.com/us/blog/how-to-read-a-ups-datasheet/) [All guides](https://www.aecups.com/us/blog/)

Products in this article

## See them in detail.

### ETHERNO

Lithium

10–30 kVA · 208 V

Online double-conversion UPS for three-phase 208 V loads from 10 to 30 kVA, in a tower cabinet, with hot-swappable 50 Ah lithium modules.

View series

### RADIANT

VRLA

15–90 kVA · 208 V

Modular online UPS with N+X redundancy for three-phase 208 V loads from 15 to 90 kVA, with an external VRLA battery bank.

View series

### CIRRO-IB

4-wire · 3P+N VRLA

30–150 kVA · 480 V 4-wire · 3P+N

Modular online UPS with N+X redundancy for three-phase 480 V, 4-wire loads from 30 to 150 kVA, with internal hot-swappable VRLA battery trays.

View series

## Talk to an engineer

Tell us the load, the voltage and the minutes you need. We answer with the model and the batteries that fit.

[Send your project](https://www.aecups.com/us/contacts/#form) [+1 786 553 2100](tel:+17865532100)