Example designs
UPS example designs: office, hospital, data centre.
A small and a medium office, a hospital and a 2N data centre: each with the UPS room to scale and the single-line diagram, at 230 or 400 V, with the AEC equipment at the EMEA 2026 catalogue's size.
Illustrations, not customer installations, and not for construction: AEC equipment is drawn from the EMEA 2026 catalogue's sizes and weights, everything else is by others and drawn for scale only. Ratings are nominal; the project's designer designs every job, and our engineers size the AEC part of it.
Example design 1 of 4
Small office, 230 V
A 200 m² office: the network rack on a 3 kVA IST3-J (2U), the reception desk on a 1 kVA IST3 tower.
Backup time
How long it holds: small office
The design's set-up in bold (IST3J-3-6X9), the same UPS's other batteries behind it: move the load, type it in kW or slide along the chart. AEC's minutes, new batteries.
Table: every set-up at 30, 50, 70 and 100 % load
| Set-up | 30% load | 50% load | 70% load | 100% load |
|---|---|---|---|---|
| IST3-J 3 kVA, 6 × 12 V 9 Ah, internalIST3J-3-6X9 | 18 min* | 8 min | 4 min | 2 min |
| IST3-J 3 kVA, 12 × 12 V 9 Ah, BBJIST3J-3-12X9 | 47 min* | 24 min | 14 min | 8 min |
| IST3-J 3 kVA, 18 × 12 V 9 Ah, 2 × BBJIST3J-3-18X9 | 78 min* | 41 min | 26 min | 15 min |
| IST3-J 3 kVA, 24 × 12 V 9 Ah, 3 × BBJIST3J-3-24X9 | 113 min* | 56 min | 38 min | 24 min |
| IST3-J 3 kVA, 30 × 12 V 9 Ah, 4 × BBJ2IST3J-3-30X9 | 155 min* | 78 min | 50 min | 30 min |
* calculated with AEC's method (1.70 V/cell, 96 %), scaled to AEC's published 50 % figure; the rest published by AEC (EMEA portal).
Example design 2 of 4
Medium office, 400 V
An office over several floors: an IST7-40 S with its internal batteries in the electrical room, a UPS board for the server room and the critical desks.
Backup time
How long it holds: medium office
The design's set-up in bold (IST7-40-80X9), the same UPS's other batteries behind it: move the load, type it in kW or slide along the chart. AEC's minutes, new batteries.
Table: every set-up at 30, 50, 70 and 100 % load
| Set-up | 30% load | 50% load | 70% load | 100% load |
|---|---|---|---|---|
| IST7-40, 80 × 12 V 9 Ah, internalIST7-40-80X9 | 18 min* | 8 min | 4 min | 2 min |
| IST7-40, 72 × 12 V 9 Ah, internalIST7-40-72X9 | 15 min* | 6 min | 3 min | 2 min |
| IST7-40, 36 × 12 V 24 Ah, BB5IST7-40-36X24 | 22 min* | 10 min | 5 min | 3 min |
| IST7-40, 38 × 12 V 24 Ah, BB5IST7-40-38X24 | 24 min* | 11 min | 5 min | 3 min |
| IST7-40, 40 × 12 V 24 Ah, BB5IST7-40-40X24 | 25 min* | 12 min | 5 min | 3 min |
| IST7-40, 30 × 12 V 40 Ah, BB5IST7-40-30X40 | 34 min* | 16 min | 9 min | 4 min |
| IST7-40, 32 × 12 V 40 Ah, BB5IST7-40-32X40 | 39 min* | 18 min | 10 min | 5 min |
| IST7-40, 144 × 12 V 9 Ah, BB4IST7-40-144X9 | 41 min* | 21 min | 12 min | 6 min |
* calculated with AEC's method (1.70 V/cell, 96 %), scaled to AEC's published 50 % figure; the rest published by AEC (EMEA portal).
Example design 3 of 4
Hospital critical loads, 400 V
The UPS board of a surgical block: an IST6-120 with four 30 kVA modules, 90 kVA N+1, one BB7 battery cabinet with 40 × 100 Ah blocks, after the mains / generator changeover.
Backup time
How long it holds: hospital
The design's set-up in bold (IST6-120-40X100), the same UPS's other batteries behind it: move the load, type it in kW or slide along the chart. AEC's minutes, new batteries.
Table: every set-up at 30, 50, 70 and 100 % load
| Set-up | 30% load | 50% load | 70% load | 100% load |
|---|---|---|---|---|
| IST6-120, 4 × 30 kVA, 40 × 12 V 100 Ah, BB7IST6-120-40X100 | 42 min* | 20 min | 10 min | 7 min |
| IST6-120, 4 × 30 kVA, 36 × 12 V 80 Ah, BB7IST6-120-36X80 | 25 min* | 10 min | 7 min | 4 min |
| IST6-120, 4 × 30 kVA, 30 × 12 V 100 Ah, BB7IST6-120-30X100 | 27 min* | 11 min | 7 min | 4 min |
| IST6-120, 4 × 30 kVA, 40 × 12 V 80 Ah, BB7IST6-120-40X80 | 28 min* | 12 min | 8 min | 4 min |
| IST6-120, 4 × 30 kVA, 34 × 12 V 100 Ah, BB7IST6-120-34X100 | 31 min* | 14 min | 8 min | 5 min |
| IST6-120, 4 × 30 kVA, 36 × 12 V 100 Ah, BB7IST6-120-36X100 | 35 min* | 16 min | 9 min | 5 min |
| IST6-120, 4 × 30 kVA, 60 × 12 V 80 Ah, BB8IST6-120-60X80 | 51 min* | 25 min | 14 min | 8 min |
| IST6-120, 4 × 30 kVA, 64 × 12 V 80 Ah, BB8IST6-120-64X80 | 54 min* | 27 min | 16 min | 9 min |
* calculated with AEC's method (1.70 V/cell, 96 %), scaled to AEC's published 50 % figure; the rest published by AEC (EMEA portal).
Example design 4 of 4
Data centre 2N, 400 V
Two separate UPS rooms, A and B: in each an IST6 600 kVA with six 100 kVA modules and L6 lithium cabinets, each one for the whole IT load.
Backup time
How long it holds: data centre
The design's set-up in bold (IST6-600-L6-80X50), the same UPS's other batteries behind it: move the load, type it in kW or slide along the chart. AEC's minutes, new batteries.
At 50 % of the rating
IST6-600H, 6 × 100 kVA
This design 4 × L6, 80 × 50 Ah lithium41 min3 × L6, 60 × 50 Ah lithium31 min5 × L6, 100 × 50 Ah lithium52 min6 × L6, 120 × 50 Ah lithium62 min7 × L6, 140 × 50 Ah lithium73 min8 × L6, 160 × 50 Ah lithium83 min9 × L6, 180 × 50 Ah lithium93 min10 × L6, 200 × 50 Ah lithium104 minTable: every set-up at 30, 50, 70 and 100 % load
| Set-up | 30% load | 50% load | 70% load | 100% load |
|---|---|---|---|---|
| IST6-600H, 6 × 100 kVA, 4 × L6, 80 × 50 Ah lithiumIST6-600-L6-80X50 | — | 41 min | 30 min | 21 min |
| IST6-600H, 6 × 100 kVA, 3 × L6, 60 × 50 Ah lithiumIST6-600-L6-60X50 | — | 31 min | 22 min | 16 min |
| IST6-600H, 6 × 100 kVA, 5 × L6, 100 × 50 Ah lithiumIST6-600-L6-100X50 | — | 52 min | 37 min | 26 min |
| IST6-600H, 6 × 100 kVA, 6 × L6, 120 × 50 Ah lithiumIST6-600-L6-120X50 | — | 62 min | 44 min | 31 min |
| IST6-600H, 6 × 100 kVA, 7 × L6, 140 × 50 Ah lithiumIST6-600-L6-140X50 | — | 73 min | 52 min | 36 min |
| IST6-600H, 6 × 100 kVA, 8 × L6, 160 × 50 Ah lithiumIST6-600-L6-160X50 | — | 83 min | 59 min | 41 min |
| IST6-600H, 6 × 100 kVA, 9 × L6, 180 × 50 Ah lithiumIST6-600-L6-180X50 | — | 93 min | 67 min | 47 min |
| IST6-600H, 6 × 100 kVA, 10 × L6, 200 × 50 Ah lithiumIST6-600-L6-200X50 | — | 104 min | 74 min | 52 min |
How to read them
The sheets, like a design set.
Each application has the two sheets an electrical design starts from.
Questions
What people ask
Can these drawings be used for a project?
No: they are examples, not real sites and not for construction. AEC equipment is drawn at the EMEA 2026 catalogue's sizes and weights; everything else is by others, drawn to scale. The project's designer designs; AEC's engineers size the AEC part.
Can I have the CAD files?
Yes, with your project: send us the plan and the single-line diagram, and an AEC engineer returns the AEC equipment, its batteries and its footprint in DWG.
Talk to an AEC engineer
Tell us the load, the supply and the backup time you need: we answer with the model and the batteries that fit.